Example Asbestos Removal Projects in Lakeville

Below are six example jobs in Lakeville, Credit River and Farmington. For each one you can read which materials get sampled, what a licensed crew removes, how many days it runs and an approximate cost.

Wall and ceiling samples before a gas fireplace goes into a family room

Example project

Home
Lakeville two-story built in the mid-1980s, family room on the main floor
Original request
Open an outside wall of the family room for a gas fireplace and its vent
Testing
Four samples by an MDH-certified inspector: the drywall, the taping mud at a seam, the wall texture and the ceiling texture
Results
All four samples come back negative
Timeline
About an hour at the house, and the lab report a few days later
Estimated testing cost
$450

Scope of work

One visit by an MDH-certified inspector, four samples from the wall the installer will cut and the ceiling right above it, a result for each sample from an accredited lab and a short written report. With nothing positive, no removal is needed.

Project overview

In this example, the owners of a mid-1980s house in Lakeville are adding a gas fireplace to their family room. The installer will cut a framed opening into the outside wall and run the vent through it, and asks for a test of the wall and ceiling finishes before any cutting starts.

The house was built before October 1988, so a builder letter is not an option, and four samples settle the question. All four come back with no asbestos, and the fireplace goes in on the date the installer set.

The goal

The goal is a clear answer before the saw comes out, so the fireplace goes in without a delay.

Process

  1. First visit Four small cores from the family room wall and ceiling, taken by an MDH-certified inspector at the fireplace spot.
  2. At the lab Each sample is analyzed on its own and given a result.
  3. A few days later The report lists the four materials, where each came from and what the lab found.
  4. Then The owners pass the report to the installer, who starts cutting.

Planning right

  • Outline the fireplace opening in pencil so the inspector knows exactly where to cut.
  • The report records which materials were sampled and where. Anything else, like the floor, needs its own sample before it is disturbed.
  • Keep the report with the house papers.
  • Patch the small sample spots, or leave them for the installer to cut out.

Get a free quoteMore about asbestos testing and surveys

Popcorn ceilings scraped before two small bedrooms become one large bedroom

Example project

Home
1970s split-entry house in Lakeville with two small bedrooms side by side on the upper level
Original request
Take out the wall between the bedrooms and finish one smooth ceiling over the new room
Testing
Samples by an MDH-certified inspector of the popcorn texture in each bedroom and the taping mud on the wall between them
Found
Asbestos in the popcorn texture in both bedrooms
Clear
No asbestos in the taping mud on the wall that comes out
Area
About 220 sq ft of ceiling across the two rooms
Timeline
Five-day notice, then two working days
Cost
$3,100

Scope of work

Samples of both ceilings and the dividing wall, the MDH notice filed five days ahead, both bedrooms emptied and closed in plastic with a HEPA air machine running, the light fixtures and smoke alarms taken down, the texture misted and scraped into sealed bags, air samples, a HEPA clean and disposal with its manifest. Taking out the wall and finishing the ceiling are the carpenter’s work.

Project overview

In this example, a family with a 1970s split-entry house in Lakeville wants one large bedroom upstairs in place of two small ones. The carpenter will take out the wall between them and patch the ceiling where it stood, and the owners want one smooth ceiling across the new room.

The popcorn texture in both rooms tests positive, and the taping mud on the dividing wall does not. A licensed crew scrapes both ceilings before the wall comes down, so the carpenter starts on bare board.

The goal

The goal is two bare ceilings and a wall ready to come out, so the new bedroom gets one smooth finish.

Process

  1. First visit Both ceilings and the dividing wall sampled by an MDH-certified inspector; the rooms measured.
  2. Before work Both small bedrooms, closets and all, are packed up and emptied while the MDH notice runs.
  3. Day one The two bedrooms become one sealed work area; lights come down and the texture is wetted and scraped.
  4. Day two The room is HEPA-vacuumed and air-tested; then the plastic is bagged and taken away.

Planning right

  • Empty the closets too, since the plastic runs to the floor in both rooms.
  • The wall between the bedrooms comes down only after the air results are back.
  • The hall ceiling gets its own sample if the carpenter will work there.
  • Air sample results come with the paperwork at the end; keep them on file.

Get a free quoteMore about popcorn ceiling removal

Basement floor tile and mastic lifted so a rec room can become a home gym

Example project

Home
1970s rambler in Credit River with a carpeted basement rec room
Original request
Pull up the carpet and lay rubber gym flooring straight on the concrete for a home gym
Testing
With the carpet rolled back, an MDH-certified inspector finds old floor tile and takes it and the black mastic as two samples
Found
The tile under the carpet is positive, and so is its black mastic
Clear
No asbestos in the carpet pad glue spots or the wall paneling adhesive
Area
About 240 sq ft of floor
Timeline
Five-day notice, then two working days
Cost
$2,750

Scope of work

Samples of the tile, the mastic and the other glues in the room, the MDH notice filed five days ahead, the stair and the furnace room door sealed in plastic, the tile worked loose by hand and kept wet, the mastic taken up wet down to bare concrete, a HEPA clean, sealed bags and disposal with its manifest. The carpet haul-off and the gym floor are extra.

Project overview

In this example, the owners of a 1970s rambler in Credit River want a home gym in the basement rec room. The carpet is coming up, and the rubber flooring they picked has to sit flat on bare concrete.

Lifting one corner of the carpet shows old floor tile, and both the tile and the black mastic under it test positive. A licensed crew takes the whole floor down to concrete over two days, and the gym goes in after that.

The goal

The goal is a bare, clean slab in two days, ready for the rubber gym floor.

Process

  1. First visit An MDH-certified inspector takes the tile, its mastic and the carpet glue for testing and measures the rec room.
  2. Before work The notice goes to MDH, and the carpet stays rolled back, with the tile left alone, until the crew starts.
  3. Days one and two Stair and doors sealed, tile lifted, mastic taken up wet, the slab vacuumed and wiped.
  4. Then The gym floor goes down on bare concrete.

Planning right

  • Leave the tile alone when the carpet comes up; scraping or prying it is what breaks it.
  • Ask the gym floor seller how flat the slab needs to be.
  • The furnace room stays shut and sealed while the crew works in the rec room.
  • Keep the report: it records which floor layers were sampled and where.

Get a free quoteMore about floor tile and sheet vinyl removal

Taping mud cut out at wall openings before old plastic water lines are replaced

Example project

Home
Late-1970s two-story house in Lakeville with old water lines
Original request
Replace the water lines, with openings in the kitchen, both bathrooms and the laundry walls
Testing
Samples by an MDH-certified inspector of the drywall, the taping mud and the wall texture in each room on the plumber’s list
Found
Asbestos in the taping mud at the seams and corners
Clear
The drywall board and its texture test negative
Area
About 14 openings, about 70 sq ft of wall in all
Timeline
Five-day notice, then two working days
Cost
$2,200

Scope of work

Samples of each wall layer, the MDH notice filed five days ahead, a small sealed work area under negative air at each group of openings, the board and mud cut out wet and bagged, a HEPA clean and air samples before each area opens, and disposal with its manifest. The new water lines and the drywall patches are the other trades’ work.

Project overview

In this example, a late-1970s house in Lakeville still has its old water lines, and the owners want them replaced before one fails. The plumber marks about 14 openings in the kitchen, the two bathrooms and the laundry, wherever the old lines run inside the walls.

The drywall and the wall texture test clean, and the taping mud at the seams does not. Because the openings cross seams, a licensed crew cuts every one of them out before the plumber starts.

The goal

The goal is every opening cut and the walls clean, so the plumber can replace the old lines in one pass.

Process

  1. First visit Board, mud and texture sampled by an MDH-certified inspector in each room on the plumber’s list.
  2. Before work The notice goes to MDH, and the plumber’s marks are checked against the report.
  3. Day one Kitchen and laundry openings cut out inside small sealed work areas.
  4. Day two Both bathrooms done, air samples taken, and the bags hauled.

Planning right

  • Ask the plumber to mark every opening before the crew comes, so none has to be cut later.
  • Taping mud can test unlike the board behind it, so each gets its own sample.
  • Keep the water on until the plumber’s day; the crew does not touch the pipes.
  • The drywall patches go up after the new lines are tested.

Get a free quoteMore about drywall and joint compound removal

Cement shingles taken off a garage side wall before a third stall is added

Example project

Home
1960s rambler in Lakeville with an attached two-stall garage clad in cement siding shingles
Original request
Add a third stall to the side of the garage, joined to the old wall and roof
Testing
Samples by an MDH-certified inspector of the siding shingles, the paper behind them and the garage roof shingles
Found
Asbestos in the cement siding shingles
Clear
No asbestos in the building paper or the roof shingles
Area
About 260 sq ft of wall, gable included
Timeline
Five-day notice, then one working day
Cost
$3,200

Scope of work

Samples of the siding, the paper and the roof, the MDH notice filed five days ahead, plastic laid along the foundation, the shingles misted and taken off by hand in whole pieces, stacked and wrapped in heavy plastic, the ground picked clean and the haul with its manifest. The addition, its roof and the new siding are the builder’s work.

Project overview

In this example, a family with a 1960s rambler in Lakeville is adding a third stall to their attached garage. The builder will open the garage side wall and tie the new roof into the old one, and that wall is covered in cement siding shingles.

The shingles test positive. The paper behind them and the roof shingles do not. A licensed crew takes the whole side wall off in one day, unbroken where the shingles allow, so the framers start on bare sheathing.

The goal

The goal is one bare garage wall with nothing broken on the ground, so the third stall goes up on schedule.

Process

  1. First visit Siding, paper and roof sampled by an MDH-certified inspector; the wall and gable measured.
  2. Before work Once MDH is notified, the family parks outside and clears the shelves and bikes off the side wall.
  3. Work day Plastic down, shingles off by hand, stacked and wrapped on a pallet.
  4. Then The ground is picked clean, the wrapped shingles leave with the manifest, and the framers take over.

Planning right

  • Clear the side yard and the inside of that wall before the crew comes.
  • The rest of the house keeps its siding; only the wall the addition joins comes off.
  • If the old roof needs work where the new one ties in, the report shows it was sampled.
  • Plan the new siding so it runs across the old garage and the new stall.

Get a free quoteMore about siding and roofing removal

Asbestos cleared from an older house after its owners move into a new one on the same property

Example project

Home
1920s one-and-a-half story house in Farmington, re-sided in cement shingles years later
Original request
Take down the old house once the owners have moved into the new one built on the same property
Testing
An MDH-certified inspector surveys the old house top to bottom, cellar through attic and roof
Found
Asbestos in the basement pipe wrap, the kitchen and bathroom flooring and the cement siding shingles
Clear
Plaster and roofing both negative
Timeline
Survey; five days of MDH notice; five days of removal; demolition at least two days after that
Cost
$17,600

Scope of work

Removal of every positive material in the survey: about 80 ft of pipe wrap, about 250 sq ft of kitchen and bathroom flooring and about 1,400 sq ft of cement siding shingles, with the MDH notice, sealed and labeled bags and wrapped shingles, air samples, the manifests and the abatement papers for the demolition permit. The survey and the demolition are not included.

Project overview

In this example, a family in Farmington has built a new house on the same property as their 1920s house and moved in. The old house comes down next, and the city asks for the asbestos testing and abatement to be done, and the papers handed to the building official, before any demolition.

The survey finds wrap on the basement pipes, positive flooring in the kitchen and bathroom, and cement shingles over the old siding. A licensed crew clears all of it while the city reviews the application, and the demolition crew comes at least two days after the last bag leaves.

The goal

The goal is an empty old house with nothing positive left in it and the papers with the building official, so the demolition goes ahead as planned.

Process

  1. First visit An MDH-certified inspector walks the whole old house and writes up where each positive material sits and how much there is.
  2. Next The demolition application goes in, which the city may hold up to ten business days for a historic review, and the notice goes to MDH.
  3. Removal days Pipe wrap, flooring and siding shingles come out over five working days.
  4. Last step The survey, abatement records and manifests go to the building official before demolition.

Planning right

  • Use the survey to fill in the demolition plan’s question on how contaminants were found and disposed of.
  • Keep the survey, abatement records and manifests together for the building official.
  • Salvaging old doors or trim before demolition needs its own permit from the city.
  • Give the demolition contractor a start date two or more days past the end of abatement.

Get a free quoteMore about remodel and demolition abatement